Post Production
Production
March
(shooting/recording)
Week 4:
Captured all footage (digital video camera) at Japanese Gardens in Hayward, CA
Several clips had shaky camera work that were later trimmed
Selected music/ intro text
Post-Production
April
Week 1:
First-draft rough cut edited with Adobe Rush, submit first rough cut by 4/12/21
Added Titles and music/narration
(Teacher review 4/15/21 @ 11:00 pst/ 2:00 est)
Week 2:
Second-draft - add graphics (background, end credit template), cleanup edit and audio
Add new footage from Japanese Gardens in Bay Area, CA.
Complete narration
Plan for graphics
Find any extra footage from web if needed
Post draft on sonymcs
(Teacher review 4/21/21)
Week 3/4:
Draft review on sonymcs worksessions (meet with Teacher on 4/27/21)
Finish any effects and end credits
Completed film
Comments
Post a Comment